Image of ISO 500 and 100th Anniversary of Turkey
1.2 Megawatt Solar Power Plant from CW Enerji to Tokat

CW Enerji, which produces solar panels in Antalya Organised Industrial Zone, has completed the provisional acceptance of the solar power plant with a total installed capacity of 1.2 megawatts built in Turhal district of Tokat province. With 1.2 megawatt electrical energy capacity, it will generate 1 million 904 thousand 950 kilowatt hours of electricity per year.

CW Enerji completed the installation and provisional acceptance of the land-type solar power plant (SPP) with a total power of 1,229 kWp (Kilowatt-Peak) built in Turhal district of Tokat province in accordance with the Unlicensed Electricity Generation Regulation in the Electricity Market No. 28783 dated 02.10.2013.

In the 1,229 kWp SPP project, 4,554 TT270 WP-60P solar panels, 16 Huawei Sun2000-60KTL and 1 Huawei Sun2000-36KTL inverters manufactured by CW Enerji were used. This SPP project, in whichCWEnerji, as the contractor company, carried out panel supply, engineering and EPC (implementation), was completed in 23 days. The provisional acceptance of the project was received on 09 November 2018 and it has been made ready for operation.

The completed project, with a capacity of 1,229 kWp, will be able to meet the electricity of an average of 1075 households per year with renewable energy and will support the reduction of 1429 tonnes of carbon dioxide (CO2), 4.3 tonnes of sulphur dioxide (SO2), 1.6 tonnes of nitrogen oxide (NOX) gas emissions per year. The 1,229 kWp solar power plant is planned to generate an average of 5,219.04 kWp of electricity per day and 1,904,950 kWp per year.

21.11.2018

🍪 CW Enerji Cookie Policy

You can review our Cookie Policy to get information about the third party cookies we use as CW Enerji. Click \'Accept\' to approve our Cookie Policy.

MORE INFO